CARGILL - BROCKTON | SUNROOM ADDITION SIDING PREP, INSULATION AND DRYWALL
Cargill - Brockton | Sunroom addition siding prep, insulation and drywall
We installed an aluminum flashing over the foundation wall lapped with blueskin flashing tape, which is covered by the Pressure Treated ledger board for the future decks and then another aluminum flashing lapping all the previous work is installed and also covered in blueskin to ensure adequate water drainage in the rain screen layer.
The strapping has been completed on the addition to create a rain screen / ventilated cavity behind the siding, 16” o.c. vertical strapping then strapped 12” o.c. horizontally in preparation for the Maibec Board and Batten siding.
The wiring rough in was completed by Tim Wells Electric. The addition was insulated by Martin’s Insulation with polyurethane closed cell spray foam. Achieving an R-28 wall and R-50 ceiling. They sprayed from the footings to the peak of the roof, including capping any of the interior double brick wall and foundation to stop thermal bridging.
We installed 1/2” CGC drywall board in the sunroom with Trim Tex drywall corner beads. All supplied to us by Welbeck Sawmill.
The addition has been taped, and the cover coat ran on all the tapes and corners, screws have all been spotted a second time.
The addition has now been skim coated with our 12” Columbia box and the screw spotted a third coat, we have skimmed out the neo angles at the ceilings with our 8” Columbia box, and we came back over all the joints with a final skim coat with our 14” Columbia box.
We have sanded out all the drywall with our sander hooked to a dust extractor to minimize the dust and have now primed the drywall with primer supplied by Farlow’s Home Hardware. Can’t wait for our windows, doors and skylights to arrive!
CARGILL - BROCKTON | SUNROOM ADDITION FOUNDATION
Cargill - Brockton | Sunroom addition foundation. We recently started this sunroom addition project, which will be a start to finish project.
Walkerton Sunbelt Rentals provided this Kubota KX080-4 mini excavator we used to strip and pile the topsoil to spread on the disturbed areas after.
Excavating the material from the foundation hole and loading to be removed from the construction site.
The Miller Group provided the cement for our project. These are our freshly poured concrete footings with a keyway cut in to receive the new foundation walls for this addition.
The walls are freshly poured and have been covered with insulated tarps to protect from the temperature drops. Chemicals have been added to the cement mix to make it generate heat as well as the cement was made with hot water because of the time of year to help it cure.
The boys (Gabriel Bender and Jude Bender) took time from school to come be a part of pouring this foundation. This gets them a hands on experience at a young age and provides opportunity for the next generation to take on and experience the work organically and develop skills naturally. Work ethic is developed and skills are learned.
Farlow’s Home Hardware provided the Home Builder fibrated asphalt foundation coating to waterproof the new crawlspace.
After the foundation coating has cured we installed Delta MS foundation wrap from Farlow’s Home Hardware to provide drainage to the new crawlspace. It is wrapped down to the weeping tile which is covered in drainage stone and filter cloth before material that was removed during excavating is place back around the foundation. The weeping tile ties into a sump pail in the new crawlspace.
The foundation is backfilled and ready for the sill plates to be installed on the anchor bolts that were placed in the concrete to secure the floor system to the foundation walls.
Welbeck Sawmill delivered our floor system and we have installed the new Pressure Treated sill plates on sill gasket and Typar house wrap. This is holding the new 2” x 12” floor joists @ 12” on centre with two runs of solid blocking to ensure a floor with very little deflection. This all gets covered in a 3/4” tounge & groove plywood sub-floor which is glued and screwed.
Solid blocking ensures all the joists stay in their place, can’t twist and makes everything binds together and shares the load on the floor joists.
Would also like to give a big thank you to Jamie Kuhl of ArchLines for all the design work on this project and with the permit process to make this all happen for our customer.
After the sub-floor was completed we covered the entire floor with insulated tarps to ensure the cold stays out of the foundation until the walls are up and everything is closed in.
BERKELEY - CHATSWORTH | ECO LOG HOME RAISING THE ROOF & DORMERS
Berkeley - Chatsworth | Eco Log Home raising the roof & dormers. We completed all the roof framing and dormers. We also installed all the roof buildups and roof insulation for the home.
2”x6” dormer walls set and ceiling joists placed on 16” centers.
Laying out for the collar ties that will be installed.
Because of the time of year the openings were tarped every night to keep the snow out of the home.
JCB getting pieces laid out and cut for the guys as they get the dormers framed up.
First half of the roof completed and ready for the future steel roofing.
Walls set on the second half of the roof for the last 2 dormers going on.
We are a family business and everyone pitches in. Alisha came in to help make sure our site stayed safe and clean for us.
The hemlock ceiling boards where all left long until the end on the gables. This allowed us to snap a perfectly straight chalk line to cut them too. We were able to manipulate the 4” x 10” trusses then to follow our perfect line keeping the ends very straight and clean looking.
The roof was made up of multiple layers. First the 1” x 6” hemlock ceiling boards went down. Then a synthetic roofing membrane was installed with ice and water shield in the valleys. Next we installed two layers of Styrorail insulation. A base layer of 3” SR.P200 Graphite which can’t stay exposed to any sunlight and then a second layer of 3.5” SR.Radiant+ which has a vapour barrier reflective membrane laminated to it. All layers have offset joints which where taped with Tuck Tape sheathing tape. We then cover the valleys & dormers with an additional layer of GRACE Ice and Water Shield HT. Finally all this is covered with a layer of 2x4 sheathing installed @ 16” o.c. for the new steel roofing.
Over the balconies at the gable ends and the porches we used a 2x8 rafter build up to match the 6-1/2” of insulation and then installed the 2x4 sheathing over top of them @ 16”o.c.
Completed jack rafters forming the valleys of the home with collar ties installed to prevent any uplift or separation from the roof peak.
We pulled some large tarps over the home at the completion of our work to leave the home ready for the new steel roof install.