CARGILL - BROCKTON | SUNROOM ADDITION FOUNDATION

Cargill - Brockton | Sunroom addition foundation. We recently started this sunroom addition project, which will be a start to finish project.

Kubota KX080-4 Mini Excavator excavating for a foundation

Walkerton Sunbelt Rentals provided this Kubota KX080-4 mini excavator we used to strip and pile the topsoil to spread on the disturbed areas after.

Kubota KX080-4 mini excavator excavating a loading a dump trailer on a Case Maxxum 125 Loader Tractor

Excavating the material from the foundation hole and loading to be removed from the construction site.

Foundation footings poured and keyed for an addition

The Miller Group provided the cement for our project. These are our freshly poured concrete footings with a keyway cut in to receive the new foundation walls for this addition.

Foundation footings poured and keyed
Foundation walls poured and covered with insulated tarps

The walls are freshly poured and have been covered with insulated tarps to protect from the temperature drops. Chemicals have been added to the cement mix to make it generate heat as well as the cement was made with hot water because of the time of year to help it cure.

my boys the next generation

The boys (Gabriel Bender and Jude Bender) took time from school to come be a part of pouring this foundation. This gets them a hands on experience at a young age and provides opportunity for the next generation to take on and experience the work organically and develop skills naturally. Work ethic is developed and skills are learned.

Tar foundation coating applied to waterproof foundation, JCB and Sons, Archlines, Farlow's Home Hardware, Cement, Foundation, Waterproofing, Addition, Brockton, Cargill

Farlow’s Home Hardware provided the Home Builder fibrated asphalt foundation coating to waterproof the new crawlspace.

Delta MS foundation wrap applied with weeping tile, drainage stone and filter cloth

After the foundation coating has cured we installed Delta MS foundation wrap from Farlow’s Home Hardware to provide drainage to the new crawlspace. It is wrapped down to the weeping tile which is covered in drainage stone and filter cloth before material that was removed during excavating is place back around the foundation. The weeping tile ties into a sump pail in the new crawlspace.

Delta MS foundation wrap, weeping tile, drainage stone and filter cloth applied to foundation
JCB and Sons, Archlines, addition, renovation, Brockton, Cargill, new build, carpentry
Foundation backfilled ready for floor assembly with our Branson 3820 Tractor, JCB and Sons, Archlines, Addition, renovation, building, new build, foundation

The foundation is backfilled and ready for the sill plates to be installed on the anchor bolts that were placed in the concrete to secure the floor system to the foundation walls.

Floor joists installed on new foundation walls after backfilling, JCB and Sons, archlines, addition, renovation, new build, carpentry, brockton, Cargill, builder, Welbeck Sawmill

Welbeck Sawmill delivered our floor system and we have installed the new Pressure Treated sill plates on sill gasket and Typar house wrap. This is holding the new 2” x 12” floor joists @ 12” on centre with two runs of solid blocking to ensure a floor with very little deflection. This all gets covered in a 3/4” tounge & groove plywood sub-floor which is glued and screwed.

Solid blocking installed between floor joists to make floor assembly rigid, JCB and Sons, Archlines, builder, renovation, carpentry, framing, addition

Solid blocking ensures all the joists stay in their place, can’t twist and makes everything binds together and shares the load on the floor joists.

New floor assembly framed on the new foundation walls, JCB and Sons, Archlines, renovation, addition, new build, foundation, framing, builder, Brockton, Cargill

Would also like to give a big thank you to Jamie Kuhl of ArchLines for all the design work on this project and with the permit process to make this all happen for our customer.

Insulated tarps pulled over the floor assembly to keep frost out of the new crawlspace

After the sub-floor was completed we covered the entire floor with insulated tarps to ensure the cold stays out of the foundation until the walls are up and everything is closed in.

Read More
Log Home, New House Builds, Roofing Christian Bender Log Home, New House Builds, Roofing Christian Bender

BERKELEY - CHATSWORTH | ECO LOG HOME RAISING THE ROOF & DORMERS

Berkeley - Chatsworth | Eco Log Home raising the roof & dormers. We completed all the roof framing and dormers. We also installed all the roof buildups and roof insulation for the home.

Eco Log Home winter roof framing
JCB cutting framing with Makita circular saw
Inside of Eco Log Home loft dormer

2”x6” dormer walls set and ceiling joists placed on 16” centers.

Laying out for the collar ties that will be installed.

Because of the time of year the openings were tarped every night to keep the snow out of the home.

JCB laying out lumber for roof framing

JCB getting pieces laid out and cut for the guys as they get the dormers framed up.

JCB cutting framing with Makita Circular Saw

First half of the roof completed and ready for the future steel roofing.

Walls set on the second half of the roof for the last 2 dormers going on.

We are a family business and everyone pitches in. Alisha came in to help make sure our site stayed safe and clean for us.

Guys air nailing dormer wall framing together on loft floor
dormer walls going on roof covered with a green tarp.

The hemlock ceiling boards where all left long until the end on the gables. This allowed us to snap a perfectly straight chalk line to cut them too. We were able to manipulate the 4” x 10” trusses then to follow our perfect line keeping the ends very straight and clean looking.

The roof was made up of multiple layers. First the 1” x 6” hemlock ceiling boards went down. Then a synthetic roofing membrane was installed with ice and water shield in the valleys. Next we installed two layers of Styrorail insulation. A base layer of 3” SR.P200 Graphite which can’t stay exposed to any sunlight and then a second layer of 3.5” SR.Radiant+ which has a vapour barrier reflective membrane laminated to it. All layers have offset joints which where taped with Tuck Tape sheathing tape. We then cover the valleys & dormers with an additional layer of GRACE Ice and Water Shield HT. Finally all this is covered with a layer of 2x4 sheathing installed @ 16” o.c. for the new steel roofing.

Over the balconies at the gable ends and the porches we used a 2x8 rafter build up to match the 6-1/2” of insulation and then installed the 2x4 sheathing over top of them @ 16”o.c.

Completed jack rafters forming the valleys of the home with collar ties installed to prevent any uplift or separation from the roof peak.

We pulled some large tarps over the home at the completion of our work to leave the home ready for the new steel roof install.

Read More
Christian Bender Christian Bender

BERKELEY - CHATSWORTH | ECO LOG HOME & TIMBER FRAME

Berkeley - Chatsworth | Eco Log Home & Timber Frame. We were contracted to come be a part of this Eco Log Home build. The home owner had taken on this project himself and contracted us to build his timber frame porches and complete the roof assembly.

Eco Log Home trusses installed and ceiling boards being installed

4” x 10” roof trusses all set @ 4’-0” on centre. This is covered with 1” x 6” Hemlock boards to complete the interior ceiling. The ceiling boards are then covered with a synthetic roofing membrane ready for the insulation layers to go on.

Eco Log Home trusses set and ceiling boards going on
Sophie the Carpenter dog, red fawn boxer
Scenic shot of Eco log home, trusses set and ceiling boards going on with synthetic roofing membrane
Makita chain mortiser cutting mortises in Hemlock beam

John Bender cutting mortises on site with our chain mortiser for the assembly of the post and beams to build the porches

Trimming back subfloor to be flush with rim board

Cleaning up the sub floor to allow for the install of Blueskin flashing tape and aluminum flashing prior to installing the porch deck frames.

Prepping Blueskin flashing tape to protect rim board around home

Rolling out Bluesking Flashing Tape to waterproof the rim joist around the home.

Cutting mortise with Makita chain mortiser
Close up of Makita chain mortiser making wood chips
Carpenter in training Jude Bender

Jude Bender

Jude Bender and Christian Bender in front of Log Home
Using a chisel to fine tune tenons to fit mortises

Fine tuning the mortises by hand to fit perfectly into the tenons we cut.

Using a large dead blow to drive the tenons into mortises of the beam and posts

Driving the tenons on the posts and knee braces into the mortises of the beams.

Adding a ratchet strap to post and beam assembly to create pressure to draw mortise and tenons tight
Using dead blow and mallet to drive the post and beam together
Red Oak dowels cut are ready to peg the mortise and tenons together

Red oak dowels used to peg the mortise and tenons together.

High fiving after the mortise and tenons have drawn perfectly tight
Drilling through mortise and tenon to peg with oak dowels

Drilling holed through the assembled mortise and tenons to receive the red oak dowel pegs.

oak dowels installed through mortise and tenons
Trimming the tenons with a 10" beam saw

Adjusting a tenon to fit perfectly into the mortises with a 10” beam saw.

first snow with erected timber frame and new decks built

First snow of the season.

erected timber frame and deck
Eco log home and timber frame deck
8" x 8" knee brace with tenon

8” x 8” Hemlock knee brace with tenon.

Porch post with cut tenon and mortise for knee brace

Porch post with tenon on top and mortise for knee brace on the side.

mortises in porch beam for post and knee braces
Finished scarf joint

Scarf joint to make the beam pieces long enough to support the porch deck assembly.

Porch posts and beam all pegged together and ready to be erected
steel plate installed on bottom of porch posts

Steel plates are screwed to the bottom of the posts which will sit on top of a threaded bold and nut allowing for adjustment as the log home wall shrink with time.

zoom boom lifting completed porch post and beam assembly up to finish position

Using a Genie Zoom Boom to lift the post and beam assemblies into their final place to support the porch roofs.

zoom boom lifting second porch post and beam assembly up into finished position
completed porch post and beam assemblies erected and snowing now
Eco Log Home with all ceiling boards on and roof membrane down and completed porches

All the hemlock ceiling boards on and covered with synthetic roof membrane. Porches completed. Ready for dormers to go on the home and insulation board.

Eco Log Home with completed ceiling boards on trusses roof membrane installed and completed timber frame porches
Read More