WEST GREY BASEMENT RENOVATION, WIRING, INSULATION, AND NEW BATHROOM ROUGH IN | JCB and SONS
West Grey Basement Renovation, Wiring, Insulation, and new Bathroom rough in | JCB and SONS. Winter has given us some time to tackle our own home and renovate our own very poorly finished basement. We decide to add an additional bathroom. Adding a
in our basement. This required removing the cement floor and excavating to install ABS drains and the tank. We also moved our sump pail while we were doing all of this work to a more suitable location.
We removed all the old drywall which was very poorly done and had some mildew because of the poor vapour barrier and things not being sealed properly
Here you can see the ice on our walls because of the improper insulation and vapour barrier.
For this we moved majority of our basement things to the garage, the remainder was moved to the middle for this portion of the job.
The pink fiberglass insulation in this picture would have provided an R-12 when it was originally installed. It was in very poor shape, and was even destroyed completely in places because of mice. You can see all their tunnel in the insulation here.
Andy Baker came from
Integrated Audio Visual and Event
to run
Networking cable, and he also installed speaker wire for our home theatre system.
Integrated Audio Visual and Event Management
created a network with a central hub that ties in our office space, our home theatre area, and our living room. We also ran conduit for any future connections that need to be made.
Here is a panorama of the finished home theater and network cables by
Integrated Audio Visual and Event Management
. It was a great time to install all this while the walls were open.
We had
from Tara come to
our basement with 3" of foam. Providing
for our basement and a continuous vapour barrier. Creating a very warm and dry basement.
WEST GREY FLOOR POUR FOR 24' X 36' GARAGE | JCB and SONS
Testing the power screed before we get started.
We installed
house wrap on the garage so that it would be ready to be insulated in the future.
The same siding as on the house was installed on the new garage to insure a good match to the customers home.
ROOF FRAMING IS ALMOST DONE IN WEST GREY | JCB and SONS
Roof framing is almost done in West Grey | JCB & SONS. The trusses are set and ready for fascia boards
Birds eye view of our new trusses set and braced for the night.
Look outs are installed and fascia boards are on. We even have one side almost sheeted with new 1/2" Spruce Plywood.
Took the opportunity to take a picture of the new shingle roof and skylights we installed last September for this customer.