ELECTRICAL, PLUMBING, HVAC STAGE OF PRICEVILLE RENO | JCB AND SONS
Electrical, Plumbing, HVAC stage of Priceville Reno | JCB & SONS. We have installed the new
. This adds a breathable layer of moisture protection to the outside of the home before the siding is installed ensuring the elements can't get in but your wall cavity can breath keeping it dry.
We installed really strong collar ties to ensure this rafter roof will stand another 100 years and also as bracing for the demolition portion of the job. The roof has dipped a bit over the years, so this has locked everything into place. We have now combined those collar ties with new 2" x 8" ceiling joists.
The basement walls are all framed up and ready for all the wiring, plumbing, insulation.
Because of the span on the rafters we also strapped all the ceiling with 2" x 4" @ 16" o.c. to install our drywall. This also further contributes to tying the old walls together and strengthening the old roof.
The pink things in the roof are
. These are a must to allow an air space between your insulation and roof sheathing. It allows your attic to vent properly thus preventing
1 and also making your shingles last much longer.
The one bedroom and bathroom will be receiving pocket doors. The entire second floor will be receiving spray foam insulation.
The back half of the roof has been stripped of all the old shingles and the roof sheathing has been repaired and re-nailed. We installed two runs of
along the eaves and also one run in the valley's. We covered the remainder of the roof in
. This meets Ontario Building Code, keeps the house dry until shingled, and also meets the shingle manufactures requirements to be covered under their warranty. If the roof fails prematurely and this isn't done you will not be covered under warranty.
All of the heat runs and cold air returns are in for the first and second floors. The landing is also in for the new stairs.
This wall is for the laundry shoot and also created a chase for the main plumbing stack for the house.
has done an awesome job or wiring our project up, they will be roughing in for an alarm system, central vac, as well as a generator back up.
All of our plumbing rough in is in and passed inspection this week ready for insulation and drywall.
is installing an awesome high efficiency propane furnace,
, air conditioning. This will have the home comfortable all year round and with healthy clean air to breath.
We all started young in the Bender family on a broom. Clean job sites are important to us!
WEST GREY, DURHAM BASEMENT RENOVATION, FRAMING, AND DRYWALL | JCB & SONS
West Grey, Durham Basement Renovation, Framing, and Drywall | JCB & SONS. We have been back at our place working like mad trying to get our basement, and office renovation done. We completed the installation of a brand new
and Duct Work and all the framing for the bulk heads, and have started the drywall.
You can see the main runs of duct work from our brand new
that feed fresh air to our home and remove the stale air, creating a very healthy environment for our family. We framed a bulk head around them to hide the ducting. We absolutely love our new spray foam insulation in the basement, it has been amazingly warm in our house during these freezing temperatures the last few weeks.
This is the utility room with updated plumbing, and a new
that we installed for emergency use.
Here you can see where we installed our new
in the basement bedroom closet. It will be easily accessible to clean the HRV filters every 3 month here and, to do yearly maintenance. It also was an ideal location to run the ducts and it was on an exterior wall so that we can access nice fresh air, and exhaust the stale air.
We now have our sewage pump all hooked up which will handle pumping the waste water from our basement bathroom when it's completed.