PRICEVILLE FARMHOUSE ROUGH IN COMPLETED AND BASEMENT WATERPROOFED | JCB AND SONS
Priceville farmhouse rough in completed and basement waterproofed | JCB & SONS.
completed the rough in for electrical, backup generator, security and central vac. Plumbing rough in is done and
completed the furnace rough in.
We installed
Gaf | Timberline Architectural Lifetime Roofing Shingles
on this project. 6' of ice and water shield was installed on the eaves and ice and water in the valleys as well as steel valley flashings. The remainder of the roof was covered in synthetic felt paper.
We also installed a vent-a-ridge which goes under the ridge cap to make a continuous roof vent which is hidden very well.
We also installed almost 400 brick ties in the old home tying the old structure into the new structure we built inside of it prior to polyurethane foam insulating.
We took the time to drywall the ceiling in the addition prior to insulating. We than had 2" of foam insulation sprayed over the drywall, potlights, speakers, etc. We will top this up with cellulose to achieve an R-50 in the addition attic. This ensures an airtight seal around all the fixtures and against the exposed brick wall between the old home and the addition.
We added this Pent Roof over the living room window which looked out of place prior to the renovation because it was added later and not trimmed the same. All the openings in the brick have arches except this one. This added an element of curve to this window, it should also tie in well with the future porch around the addition.
The addition foundation was cement block and leaked badly all the time, especially in the spring or after rains. We excavated around the foundation to waterproof it. We pressure washed the old foundation as well so the waterproofing would bond to a clean surface.
Hydro One came in and disconnect power and installed the new underground cable from the hydro pole at the road to the new meter base WireQ installed.
WireQ installed a disconnect switch to add in a future back up generator as well as a new 200amp breaker panel.
During excavating we found the missing well, which is illegal as it was below grade and would have run off going in the exposed well head. The cement block foundation had a lot of cracks. We V'd them out with a diamond blade and filled them with non-shrink grout which was than coated with fibreglass resin by MBS prior to tarring it.
We installed new septic tank risers on the old septic tank to make locating and cleaning the tank easy.
We eliminated the old sump pail by digging in this trench and installing pipe for the weeping tile and a separate pipe for eavestrough creating a french drain to remove the water far from the foundation.
The front door sill was all gone and rotten. We poured in a new cement sill after having the ring joist coated in spray foam first.
sprayed all the walls with R-24 spray foam, the old house sloped ceiling received R-50 spray foam and the addition received R-12 spray foam and will be topped up to R-50 with cellulose.
Martins Insulation insulated the basement walls with R-24 Spray foam.
We tied the new weeping tile into our new french drain, which we also installed a cleanout in just in case. We ran a separate line than to tie the eavestrough into.
We than backfilled the foundation with 2' of washed stone and than gravel on top to ensure great drainage around the foundation as the property does slope into this home.
The white pipe on the left is the cleanout for the weeping tile ensuring it can never plug. The white pipe on the right is for the future eavestrough to tie into. Keeping the water away from the basement.
ELECTRICAL, PLUMBING, HVAC STAGE OF PRICEVILLE RENO | JCB AND SONS
Electrical, Plumbing, HVAC stage of Priceville Reno | JCB & SONS. We have installed the new
. This adds a breathable layer of moisture protection to the outside of the home before the siding is installed ensuring the elements can't get in but your wall cavity can breath keeping it dry.
We installed really strong collar ties to ensure this rafter roof will stand another 100 years and also as bracing for the demolition portion of the job. The roof has dipped a bit over the years, so this has locked everything into place. We have now combined those collar ties with new 2" x 8" ceiling joists.
The basement walls are all framed up and ready for all the wiring, plumbing, insulation.
Because of the span on the rafters we also strapped all the ceiling with 2" x 4" @ 16" o.c. to install our drywall. This also further contributes to tying the old walls together and strengthening the old roof.
The pink things in the roof are
. These are a must to allow an air space between your insulation and roof sheathing. It allows your attic to vent properly thus preventing
1 and also making your shingles last much longer.
The one bedroom and bathroom will be receiving pocket doors. The entire second floor will be receiving spray foam insulation.
The back half of the roof has been stripped of all the old shingles and the roof sheathing has been repaired and re-nailed. We installed two runs of
along the eaves and also one run in the valley's. We covered the remainder of the roof in
. This meets Ontario Building Code, keeps the house dry until shingled, and also meets the shingle manufactures requirements to be covered under their warranty. If the roof fails prematurely and this isn't done you will not be covered under warranty.
All of the heat runs and cold air returns are in for the first and second floors. The landing is also in for the new stairs.
This wall is for the laundry shoot and also created a chase for the main plumbing stack for the house.
has done an awesome job or wiring our project up, they will be roughing in for an alarm system, central vac, as well as a generator back up.
All of our plumbing rough in is in and passed inspection this week ready for insulation and drywall.
is installing an awesome high efficiency propane furnace,
, air conditioning. This will have the home comfortable all year round and with healthy clean air to breath.
We all started young in the Bender family on a broom. Clean job sites are important to us!